Burndown Chart

What it is

A burndown chart shows the amount of work remaining over time, usually in story points or tasks, against an ideal line that reaches zero at the end of a sprint or release. The actual line goes down as work is completed. Flat sections show no progress; rises show work added.

Why it matters

It gives a quick visual answer to the question 'are we on track?' and helps the team react early. Analysts use it in stand ups and reviews to explain progress, and a sudden rise often signals scope added mid sprint, which is worth discussing with the product owner.

Example

Halfway through a sprint at Riverbend Logistics, the burndown line is flat for three days. Looking closer, the team sees that two stories are blocked waiting for test data from the courier partner. The Scrum Master escalates, the data arrives the next day and the line starts falling again.

Used in these guides

CHECK BEFORE CONTINUING

Keep your work safe