Three Point Estimation
What it is
Three point estimation asks for three numbers for each task: an optimistic estimate, a most likely estimate and a pessimistic estimate. They are combined into an expected value, often with the formula optimistic plus four times most likely plus pessimistic, divided by six. The spread between the numbers shows how uncertain the task is.
Why it matters
A single number hides uncertainty and invites false confidence. Three numbers make people think about what could go wrong and give planners a realistic range. Analysts use it for analysis work such as discovery, data mapping or UAT support, where the unknowns are real and worth showing to the sponsor.
Example
Asked how long the data mapping for the insurance migration will take, Imran estimates four days at best, six most likely and twelve if the legacy fields are poorly documented. The expected value is about 6.7 days. The wide pessimistic number prompts the project manager to book time with the legacy system expert early.