Sprint Planning

What it is

Sprint planning is the Scrum event that starts a sprint. The team discusses why the sprint is valuable and agrees a sprint goal, decides which product backlog items can be done, and plans how to do the work, often by breaking stories into tasks. It is timeboxed, usually to a few hours for a two week sprint.

Why it matters

Good planning gives the team a realistic, shared commitment and a clear focus. Planning goes badly when stories are unclear, so analysts contribute most by making sure top backlog items are refined beforehand. During planning, the analyst answers questions and notes any new details on the stories.

Example

In sprint planning at Riverbend Logistics, the product owner proposes the goal 'drivers can record failed deliveries with a reason'. The team pulls in five stories based on its recent velocity, and the analyst clarifies the list of failure reasons. One story is too large and is split on the spot.

Used in these guides

CHECK BEFORE CONTINUING

Keep your work safe