UAT Sign Off
What it is
UAT sign off is the formal approval by business owners that user acceptance testing is complete and the solution is acceptable to go live, usually with a list of open defects and agreed workarounds. It is recorded with the name, date and any conditions attached.
Why it matters
Sign off makes the business's acceptance explicit and moves accountability for the go live decision to the right people. It is not a formality: business owners should see the evidence first. Analysts prepare that evidence, such as results by scenario, open defects with business impact and the status against exit criteria.
Example
At the end of UAT, the analyst sends the head of claims a one page summary: fifty eight of sixty scenarios passed, two severity three defects open with manual workarounds and all exit criteria met. The head of claims signs off with one condition, that both defects are fixed within a month.